This dataset describes the iron ore mining in Hebei using the shallow-hole shrinkage stoping method, with the following process steps:
1. Orebody exploration and drilling pattern design
Orebody exploration: Prior to mining, detailed geological exploration of the orebody is conducted to determine its shape, size, dip angle, and mineral composition. Based on this information, mining design is carried out.
Drilling pattern design: Based on the shape of the orebody and the thickness of the ore layer, a reasonable shallow-hole drilling layout is designed. The depth of the shallow holes typically ranges from several meters to dozens of meters, and the hole spacing and row spacing are determined according to the stability of the orebody and the extraction method. When designing the shallow-hole layout, the degree of ore liberation and blasting efficiency must also be considered.
2. Drilling and Blasting
Drilling operation: Shallow holes are drilled into the orebody according to the drill pattern design. Drilling machines typically use handheld or lightweight equipment, offering high maneuverability and suitability for working in narrow underground mine drifts. The drill hole diameter usually ranges from 50 mm to 100 mm.
Charging and blasting: Explosives are loaded into the drill holes based on the orebody characteristics and hole design for blasting. The shallow hole blasting technique effectively controls ore fragmentation and detachment, minimizing excessive damage to the orebody structure. The broken ore after each blast is recovered by gravity or mechanical means.
3. Ore Extraction
Staged Extraction: Ore extraction is typically conducted in multiple stages. After each blasting round, workers recover the broken ore, usually loading it into trucks or onto conveyor systems using mechanical or manual loading equipment for transport out of the mine.
Pillar Preservation: During extraction, portions of the ore are left intact as pillars to support the overlying ore body and surrounding rock, preventing mine collapse. These pillars are temporarily preserved and are extracted in the final phase. The arrangement and timing of pillar extraction are critical to stope stability. Pillar Recovery
Pillar recovery: After the upper portion of the ore body has been substantially extracted, the pillar recovery process begins. At this stage, smaller blasting charges may be used to detach and collapse the pillars, ensuring the stability of the underground structure.
Support and Reinforcement: After pillar recovery, the mine structure may become unstable, necessitating reinforcement. Common support methods include rock bolting and shotcreting.
5. Ore Transportation and Haulage
Transport System: In shrinkage stoping, ore transportation typically involves small-scale mechanical equipment (such as load-haul-dump machines or belt conveyors) to move the ore to the shaft hoisting station. Depending on the mine's geological conditions and design, the ore can be transported to the surface via mine cars, belt conveyors, or inclined shaft hoisting systems.
Surface Processing: Once hoisted to the surface, the ore is directed to the mineral processing plant for crushing, grinding, and mineral separation.