This dataset describes the iron ore mining using the filling method in Liaoning. The process flow is as follows:
1. Preparation phase
Tunnel excavation: Firstly, the main transportation tunnels and ventilation tunnels are excavated at the lower part of the ore body to provide access for subsequent mining. Excavation usually starts from the bottom of the ore body and advances upward layer by layer.
Ore block division: According to the geological conditions of the ore body, the ore body is divided into several horizontal layers, which are mined layer by layer. The thickness of each layer depends on the thickness of the ore body and the stability of the mining field, generally ranging from 10 to 30 meters.
2. Sectional Mining
Ore fragmentation: The ore body is fragmented using drilling and blasting techniques, and the ore is removed from the stope and transported to the surface mineral processing plant for treatment. After ore fragmentation, it is conveyed via haulage roadways to either the surface or an underground mineral processing plant.
Ore transportation: The ore is transported to the mineral processing plant for treatment using mine cars, belt conveyors, or other mechanized transport equipment.
3. Backfilling of Goaf
Backfill Materials: Commonly used materials include tailings, waste rock, cement, or paste fill. These materials are transported via pipelines to the goaf and evenly fill the void. For areas requiring higher stability, cemented backfill materials, such as a mixture of cement, slag, and tailings, are typically used.
Backfill Methods: Backfilling can be implemented using either total tailings cemented fill or waste rock fill. After backfilling, the structural stability of the stope is ensured, preventing surface subsidence or goaf collapse.
4. Upper Orebody Extraction
Stepwise Advancement: After the backfilling of the lower goaf is completed, extraction of the upper orebody proceeds progressively upward, ensuring safety and stability of the mining area.